Public-Private Partnership under Saudi Law
General
How public-private partnership works under Saudi law: PPP definition, approving bodies, contract models, risk allocation and healthcare projects.
A single modern hospital can cost hundreds of millions of riyals to build, and decades of operation, maintenance and equipment renewal follow. Many governments therefore enter into a partnership with the private sector to finance, build and run public facilities. The arrangement is known as public-private partnership, or PPP. Saudi Arabia has moved this way since launching the Privatization Program under Vision 2030, and it has a dedicated law that sets the conditions of a partnership and identifies the bodies that approve projects.
How the Law Defines a Partnership
The Private Sector Participation Law, issued by Royal Decree No. (M/63) dated 5/8/1442H, defines a public-private partnership as a contractual arrangement linked to infrastructure or a public service with a term of five years or more, in which the private party carries out two or more of design, construction, management, operation, maintenance and financing. Risks are to be allocated between the government and the private party in a clear qualitative and quantitative way, and payment depends on the level of performance(1).
It follows that many familiar government contracts fall outside the legal meaning of a partnership. A short contract to clean a hospital or supply its meals is an ordinary service contract. The law also separates a partnership from the transfer of asset ownership. In a partnership the service stays public and under state supervision, whereas a transfer of ownership means selling the asset, or a stake in it, to the private sector.
Approving Bodies and Contract Rules for a Partnership
The National Center for Privatization & PPP (NCP), established by Council of Ministers Resolution No. 355, oversees privatization in sixteen sectors, among them health, education, transport and water(2). Approval of a partnership project depends on its value. Where a single contract is worth SAR 500 million or more, the NCP board approves it; below that, a supervisory committee does. The term of a partnership contract, including renewals and extensions, may not exceed thirty years without special approval, and the NCP board must consent before a contract can include an arbitration clause or a choice of foreign law(3).
According to NCP figures released in January 2026, more than 200 projects worth about SAR 800 billion have been approved since the program began, and around 90 contracts have been signed, some transferring ownership and others under a partnership model. The National Privatization Strategy targets more than 220 partnership contracts by 2030, with over SAR 240 billion in private capital investment(4).
Why Governments Turn to Partnership
The reasons for choosing partnership are mostly financial and administrative. Capital budgets are limited, a hospital built the traditional way may take years longer, and the private sector tends to run services such as maintenance, cleaning and security more efficiently. A partnership also moves part of the financial risk to the investor. Yet private finance usually costs more than government borrowing, so a partnership is worthwhile only if efficiency gains make up the difference.
Contract Models
Models of partnership vary with the depth of the private sector’s role. The simplest form of partnership is the management or operation-and-maintenance contract, in which a private operator runs an existing facility for a fee while the state keeps ownership. Next comes design-build-finance-operate (DBFO), a partnership model used for British hospitals under the Private Finance Initiative and for Turkey’s integrated health campuses. A private consortium designs, builds and finances the hospital, then runs its non-clinical services, such as cleaning, security and maintenance, typically 25 to 30 years.
Under build-operate-transfer (BOT), the facility returns to the state when the contract ends, while under build-own-operate (BOO) the investor keeps ownership. At the far end sits the integrated clinical partnership, in which the private sector delivers both medical
and non-medical services against performance indicators. The best-known example is Queen Mamohato Memorial Hospital in Lesotho. Even so, most governments, however far they take partnership, hesitate to hand medical decisions to private operators, because tying profit to treatment raises ethical objections and is hard for any government to defend in public.
Risk Allocation
The principle of any partnership is that each party bears the risks it can control. An investor saddled with a risk it has no means to manage will price it into the contract or recover it through lower service quality. Risk in a partnership is typically allocated as follows:
- Construction cost overruns and delays, and financing risk, sit with the private party.
- Non-clinical services such as cleaning and maintenance fall to the private operator, as
- this is its field of expertise.
- Demand and occupancy risk stays with the government, so the operator has no
- incentive to influence medical decisions.
- Regulatory change is a government risk, and care quality and patient safety remain
- under state oversight whoever delivers the service.
- Force majeure, such as pandemics, is handled through insurance, since no party to the
- partnership can control it alone.
Contract Tools
The partnership contract sets this allocation out clause by clause, starting with how the operator is paid. The best-known mechanism is the availability payment, a periodic sum the government pays for making the facility available to agreed standards, with automatic deductions when performance indicators such as cleanliness, waiting times and infection rates are missed. Other tools include bank guarantees, mandatory insurance, a clause letting the government step in immediately if patient safety is at risk, and dispute resolution through experts or arbitration so that services continue throughout the partnership. Before tendering, a value-for-money analysis compares the cost of the partnership with delivering the project publicly.
Partnership in the Saudi Health Sector
In healthcare, partnership began with a single diagnostic service. In June 2023 one of the Kingdom’s first health partnership projects was awarded to Altakassusi Alliance Medical to operate and maintain radiology and nuclear medicine departments in seven hospitals in the Riyadh region for ten years, together with the country’s first remote reading and reporting of medical images(5). Patients are not charged for these services. In June 2026 the Sabic Specialised Behavioural Healthcare Hospital project in Riyadh was awarded. It has 150 beds, is worth about SAR 3.8 billion over 15 years and covers medical and non- medical operations(6). It also has 19 outpatient clinics and treats addiction. That brings it close to the clinical partnership model. In October 2026 the Ministry of Health and the NCP qualified 12 bidders for the national kidney care and dialysis services project, another health partnership now in tender(7).
Where the Difficulty Lies
Most problems in a health partnership appear after the contract is signed. A failure in a health service draws more public attention than a delayed road or bridge. The boundary between clinical and non-clinical services is not always clear. An appointment booking system counts as administrative, yet it decides when a patient sees a doctor. And a partnership contract running thirty years rests on assumptions about technology and population needs that may change long before it ends. Britain’s Private Finance Initiative, the best-known hospital partnership programme, drew wide criticism over its long-term cost, and in 2018 the UK government stopped using it for new projects.
What reassures us about the Saudi partnership experience is its gradual pace. It began with radiology and has since moved on to projects that include medical care itself. That pace gives government bodies a chance to build negotiating and oversight skills before committing to larger partnership contracts.
Frequently Asked Questions about Partnership
Is every contract between a government body and a private company a partnership? No. The Private Sector Participation Law requires a term of five years or more, at least two of design, construction, management, operation, maintenance and financing by the private party, a clear allocation of risk, and payment linked to performance.
What is an availability payment? A periodic sum the government pays for making the facility available to agreed quality standards, regardless of patient numbers, so the operator gains nothing from unnecessary procedures. It is the most common payment mechanism in a partnership contract.
How long does a partnership contract last in the Kingdom? At least five years and no more than thirty, including renewals, unless specially approved. Health partnership projects tendered so far have run between ten and fifteen years.
Sources
1. Private Sector Participation Law, issued by Royal Decree No. (M/63) dated 5/8/1442H. 2. Saudipedia, “National Center for Privatization” (in Arabic). 3. Argaam, “In Detail: The Rules Governing Privatization” (in Arabic), 1 October 2021. 4. Al-Watan, NCP figures and National Privatization Strategy targets (in Arabic), 29 January 2026. 5. International Finance Corporation, press release on the diagnostic imaging PPP award, 8 June 2023. 6. MEED, report on the award of the Riyadh behavioural healthcare hospital PPP, 23 June 2026. 7. Ministry of Health, announcement of qualified bidders for the national kidney care and dialysis project, 4 October 2026.