Delay Risk and Force Majeure in Supply Chains under Saudi Law
General
How Saudi law treats delay in supply chains: force majeure vs exceptional circumstances, shared liability, the CISG position and lessons from recent crises.
When an importer discovers that its shipment is stuck in a port closed by an emergency order, while its contract with the supplier imposes a daily penalty for delay, a dispute tends to follow quickly over whether the supplier is excused from the delay penalty or the contract stands as if nothing had happened. Once largely theoretical, this issue became familiar after a global pandemic, the blockage of the Suez Canal and disruption to shipping in the Red Sea and the Strait of Hormuz. The outcome depends on the nature of the event, the wording of the contract and each party’s place in the chain.
Force Majeure Is Not a Ready-Made Excuse
Many people invoke force majeure to justify any delay, whatever its cause, but the law is more precise. Under the Civil Transactions Law, issued by Royal Decree No. (M/191) dated 29/11/1444H and in force since December 2023, if performance becomes impossible for a reason beyond the debtor’s control, the obligation and its counterpart are extinguished and the contract is dissolved by operation of law, without a court order(1). The debtor is then not liable for delay or for non-performance. Where impossibility is partial, only the corresponding part is extinguished. The burden of proving impossibility lies with the party claiming it, and the event must have been unforeseeable at the time of contracting, unavoidable, and not caused by the debtor.
The parties may agree that the debtor bears such events, so the contract’s force majeure clause usually comes first(2).
Exceptional Circumstances: Possible but Onerous Exceptional circumstances differ from force majeure in that performance remains possible but becomes excessively onerous, as with a sudden and steep rise in freight rates. Here Article 97 allows the debtor to invite the other party to renegotiate without undue delay. If they fail to agree within a reasonable period, the court may reduce the onerous obligation to a reasonable level, and performance continues during the negotiations. Any agreement to the contrary is void(2). Many supply chain disputes over delay fall closer to this category, even when the parties wrongly call them force majeure.
Excusing the Debtor for Delay
The law relieves a debtor of liability for delay in performance where the cause lies beyond its control, provided a direct causal link is shown between the event and the delay(1). The exemption does not cover events that were foreseeable when the contract was made, or risks the debtor accepted in the contract. It protects the debtor from paying compensation for the delay, but it does not allow indefinite suspension of performance or a way out of the contract.
Causes of Delay
The sources of delay in supply chains have multiplied over the past decade. Alongside natural disasters and epidemics, companies now have to plan for delay caused by wars and security incidents, sudden economic sanctions and changes in customs rules. Operational causes of delay remain as well, such as a strike at a port, a fault in a container booking system or unexpected congestion.
Liability for Delay Is Shared
A common mistake is to assume that the supplier alone bears the consequences of a delay. The seller is responsible for delay in delivery and is excused only by proving a direct causal link between the event and the delay. The carrier is governed by special rules that cap its liability and list excepted risks, and it answers for delay in arrival under the terms
of the bill of lading. The buyer, too, can become the party responsible for a delay if it is late in opening a letter of credit or collecting goods from the port, or overlooks a customs obligation that falls on it.
In practice, risk allocation turns on the Incoterms delivery term in the contract, such as FOB, CIF or DAP, because it fixes the moment at which risk, including the risk of delay, passes from seller to buyer.
The Kingdom and the Vienna Convention
Saudi Arabia acceded to the United Nations Convention on Contracts for the International Sale of Goods in August 2023, effective September 2024, but is not bound by Part III, which deals with the obligations of seller and buyer and the remedies for breach(3). In practice, the exemption rules in that part do not apply to contracts with a Saudi party merely because of the accession. Questions of delay and exemption are referred to the law designated by the conflict-of-laws rules, which may be the Civil Transactions Law.
Measuring the Loss from Delay The loss from delay is not limited to the contractual penalty. It may include storage costs at the port, container detention charges, lost onward sales and spoilage of perishable goods. A contract should therefore state what is and is not recoverable as compensation for delay, and set a cap on the delay penalty in proportion to the contract value. Without such terms, the judge or arbitrator assesses the actual loss and may appoint an expert to calculate the effect of the delay on each party.
Drafting Clauses That Hold Up in a Crisis
A good clause on delay does more than repeat legal boilerplate. It identifies the relevant events with examples, sets a short notice deadline, requires official proof such as a chamber of commerce certificate or a documented government decision, and provides for suspension rather than immediate termination, with a cap on the length of the delay after which either party may terminate and settle the remaining obligations fairly.
Notice of a delay is often neglected. Some contracts provide that any delay in giving notice forfeits the right to rely on force majeure even if all its conditions are met, so a party can lose a sound defence simply because a message was not sent in time. The risk
of delay can also be reduced through business interruption insurance and an agreed penalty that avoids argument over the amount of loss.
Lessons from Recent Crises During the COVID-19 pandemic, the General Assembly of the Supreme Court issued Decision No. (45/M) dated 8/5/1442H. It treated the pandemic as an exceptional circumstance where performance remained possible at an unusual loss, and as force majeure where performance became impossible. It held that penalty clauses do not apply where the pandemic caused the delay, that a project may not be withdrawn from a contractor because of such a delay, that the court may increase the value of supply contracts when prices rise while the obligor bears the normal increase, and that the effect must be assessed by experts contract by contract(4).
The 2021 Suez Canal blockage showed how an incident at a single point can paralyse a global supply chain and how the cost of the delay is spread among carriers, insurers and exporters. Disruption to shipping in the Red Sea and the Strait of Hormuz then exposed the limits of traditional wording against months of delay from security risks, and many companies rewrote their contracts to cover rerouting and the costs that follow(1).
In our view, the main lesson of these crises is that companies relying on generic clauses copied from template contracts ended up weaker than those that tailored their contracts to their business. Some delay is unavoidable. What can be controlled is how clearly the contract says who bears the cost of delay. Reviewing supply and transport contracts once a year and diversifying supply routes costs far less than a dispute that drags on for years.
Frequently Asked Questions about Delay
Is a supplier excused from a delay penalty because of a general market crisis? Not automatically. It must prove that the event was beyond its control and unforeseeable at the time of contracting, and that it directly caused the delay. Pointing to a general crisis without showing its effect on this particular delay is not enough.
What is the practical difference between force majeure and exceptional circumstances? Force majeure makes performance impossible and the contract is dissolved. Exceptional circumstances make it onerous, so the parties renegotiate and the court may reduce the obligation to a reasonable level.
Can the parties agree to exclude the rules on exceptional circumstances? No. Article 97 voids any agreement to the contrary. Force majeure, by contrast, may be regulated by the parties in their contract, including how delay is handled.
Sources
1. Civil Transactions Law, issued by Royal Decree No. (M/191) dated 29/11/1444H; Al Tamimi & Company, article on regional conflict under the Civil Transactions Law, 13 April 2026. 2. Pinsent Masons, Out-Law analysis on force majeure in Saudi contracts, 11 March 2026. 3. CISG-online, “Saudi Arabia Accedes to the CISG (except Part III)”. 4. General Assembly of the Supreme Court, Decision No. (45/M) dated 8/5/1442H; Okaz (in Arabic), 17 January 2021.